Filters
Question type

Study Flashcards

Repeatedly identifying causes of variances, initiating corrective actions, and evaluating results of actions is an example of


A) efficiency.
B) effectiveness.
C) continuous improvement.
D) All of these answers are correct.

E) A) and C)
F) All of the above

Correct Answer

verifed

verified

Answer the following questions using the information below: Brennen Incorporated planned to use $24 of material per unit but actually used $25 of material per unit, and planned to make 2,000 units but actually made 2,400 units. -The sales-volume variance is:


A) $9,600 favorable
B) $2,400 unfavorable
C) $10,000 unfavorable
D) $12,000 favorable

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

If a sales-volume variance was caused by poor-quality products, then the ________ would be in the best position to explain the variance.


A) production manager
B) sales manager
C) purchasing manager
D) management accountant

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The variance that is best for measuring operating performance is the:


A) static-budget variance
B) flexible-budget variance
C) sales-volume variance
D) selling-price variance

E) All of the above
F) B) and D)

Correct Answer

verifed

verified

Answer the following questions using the information below: Hector's Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance. Answer the following questions using the information below: Hector's Camera Shop has prepared the following flexible budget for September and is in the process of interpreting the variances. F denotes a favorable variance and U denotes an unfavorable variance.    -The actual amount spent for Material A was: A) $18,800 B) $20,200 C) $19,800 D) $21,000 -The actual amount spent for Material A was:


A) $18,800
B) $20,200
C) $19,800
D) $21,000

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

Answer the following questions using the information below: Apple Valley Orchards, Inc. (AVO) , developed standard costs for direct material and direct labor. In 2011, AVO estimated the following standard costs for one of their most well loved products, the AVO classic Grandma's large apple pie which had a brown sugar coating on the top of the crust as well as including cranberry and mince ingredients in addition to the apples. Answer the following questions using the information below: Apple Valley Orchards, Inc. (AVO) , developed standard costs for direct material and direct labor. In 2011, AVO estimated the following standard costs for one of their most well loved products, the AVO classic Grandma's large apple pie which had a brown sugar coating on the top of the crust as well as including cranberry and mince ingredients in addition to the apples.    During September, AVO produced and sold 1,200 pies using 1,875 pounds of direct materials at an average cost per pound of $7.00 and 280 direct labor hours at an average wage of $14.25 per hour. -September's direct labor efficiency variance is: A) $280.00 favorable B) $280.00 unfavorable C) $210.00 favorable D) $210.00 unfavorable During September, AVO produced and sold 1,200 pies using 1,875 pounds of direct materials at an average cost per pound of $7.00 and 280 direct labor hours at an average wage of $14.25 per hour. -September's direct labor efficiency variance is:


A) $280.00 favorable
B) $280.00 unfavorable
C) $210.00 favorable
D) $210.00 unfavorable

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

Managers generally have more control over price variances than efficiency variances.

A) True
B) False

Correct Answer

verifed

verified

Answer the following questions using the information below: Manash Company manufactures tires. Some of the company's data was misplaced. Use the following information to replace the lost data: Answer the following questions using the information below: Manash Company manufactures tires. Some of the company's data was misplaced. Use the following information to replace the lost data:    -What is the total flexible-budget variance (D) ? A) $240 unfavorable B) $0 C) $1,360 favorable D) $6,640 favorable -What is the total flexible-budget variance (D) ?


A) $240 unfavorable
B) $0
C) $1,360 favorable
D) $6,640 favorable

E) B) and C)
F) C) and D)

Correct Answer

verifed

verified

If variance analysis is used for performance evaluation, managers are encouraged to meet targets using creativity and resourcefulness.

A) True
B) False

Correct Answer

verifed

verified

Although computed separately, price variances and efficiency variances should NOT be analyzed separately from each other.

A) True
B) False

Correct Answer

verifed

verified

A favorable cost variance of significant magnitude:


A) is the result of good planning
B) if investigated, may lead to improved production methods
C) indicates management does not need to be concerned about lax standards
D) does not need to be investigated

E) None of the above
F) A) and C)

Correct Answer

verifed

verified

Give at least three good reasons why an unfavorable efficiency variance for direct manufacturing labor might be reported.

Correct Answer

verifed

verified

Any three of the following:
a. More lowe...

View Answer

From the perspective of control, the direct materials price variance should be isolated at the time of purchase.

A) True
B) False

Correct Answer

verifed

verified

Answer the following questions using the information below: Manash Company manufactures tires. Some of the company's data was misplaced. Use the following information to replace the lost data: Answer the following questions using the information below: Manash Company manufactures tires. Some of the company's data was misplaced. Use the following information to replace the lost data:    -What are the actual variable costs (C) ? A) $72,800 B) $64,240 C) $62,640 D) $54,080 -What are the actual variable costs (C) ?


A) $72,800
B) $64,240
C) $62,640
D) $54,080

E) All of the above
F) A) and B)

Correct Answer

verifed

verified

Answer the following questions using the information below: The actual information pertains to the third quarter. As part of the budgeting process, the Duck Decoy Department of Wooden Figurines Incorporated had developed the following static budget for the third quarter. Duck Decoy is in the process of preparing the flexible budget and understanding the results. Answer the following questions using the information below: The actual information pertains to the third quarter. As part of the budgeting process, the Duck Decoy Department of Wooden Figurines Incorporated had developed the following static budget for the third quarter. Duck Decoy is in the process of preparing the flexible budget and understanding the results.          -The flexible budget will report ________ for the fixed costs. A) $50,500 B) $49,500 Favorable C) $49,500 D) $1,000 Unfavorable Answer the following questions using the information below: The actual information pertains to the third quarter. As part of the budgeting process, the Duck Decoy Department of Wooden Figurines Incorporated had developed the following static budget for the third quarter. Duck Decoy is in the process of preparing the flexible budget and understanding the results.          -The flexible budget will report ________ for the fixed costs. A) $50,500 B) $49,500 Favorable C) $49,500 D) $1,000 Unfavorable Answer the following questions using the information below: The actual information pertains to the third quarter. As part of the budgeting process, the Duck Decoy Department of Wooden Figurines Incorporated had developed the following static budget for the third quarter. Duck Decoy is in the process of preparing the flexible budget and understanding the results.          -The flexible budget will report ________ for the fixed costs. A) $50,500 B) $49,500 Favorable C) $49,500 D) $1,000 Unfavorable Answer the following questions using the information below: The actual information pertains to the third quarter. As part of the budgeting process, the Duck Decoy Department of Wooden Figurines Incorporated had developed the following static budget for the third quarter. Duck Decoy is in the process of preparing the flexible budget and understanding the results.          -The flexible budget will report ________ for the fixed costs. A) $50,500 B) $49,500 Favorable C) $49,500 D) $1,000 Unfavorable -The flexible budget will report ________ for the fixed costs.


A) $50,500
B) $49,500 Favorable
C) $49,500
D) $1,000 Unfavorable

E) All of the above
F) None of the above

Correct Answer

verifed

verified

Variances should be investigated:


A) when they are kept below a certain amount
B) when there is a small variance for critical items such as product defects
C) even though the cost of investigation exceeds the benefit
D) when there is an in-control occurrence

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

Cost control is the focus of the sales-volume variance.

A) True
B) False

Correct Answer

verifed

verified

The static-budget variance can be subdivided into the flexible-budget variance and the sales-volume variance.

A) True
B) False

Correct Answer

verifed

verified

The master budget is:


A) a flexible budget
B) a static budget
C) developed at the end of the period
D) based on the actual level of output

E) A) and B)
F) None of the above

Correct Answer

verifed

verified

During February the Lungren Manufacturing Company's costing system reported several variances that the production manager was surprised to see. Most of the company's monthly variances are under $125, even though they may be either favorable or unfavorable. The following information is for the manufacture of garden gates, its only product: During February the Lungren Manufacturing Company's costing system reported several variances that the production manager was surprised to see. Most of the company's monthly variances are under $125, even though they may be either favorable or unfavorable. The following information is for the manufacture of garden gates, its only product:    Required: a. Provide the manager with some ideas as to what may have caused the price variances. b. What may have caused the efficiency variances? Required: a. Provide the manager with some ideas as to what may have caused the price variances. b. What may have caused the efficiency variances?

Correct Answer

verifed

verified

a. Direct materials' unfavorable price v...

View Answer

Showing 121 - 140 of 180

Related Exams

Show Answer