A) is exactly equal to its net present value (NPV) .
B) is exactly equal to zero.
C) is less than the required return.
D) exceeds the required return.
E) is exactly equal to 100%.
Correct Answer
verified
Multiple Choice
A) the timing of the project's cash flows has no bearing on the value of the project.
B) the project will always be accepted.
C) the project will always be rejected.
D) whether the project is accepted or rejected will depend on the timing of the cash flows.
E) the project can never add value for the shareholders.
Correct Answer
verified
Multiple Choice
A) how the incremental IRR varies with changes in the discount rate.
B) how decisions concerning mutually exclusive projects are derived.
C) how the duration of a project affects the decision as to which project to accept.
D) how the payback period and the initial cash outflow of a project are related.
E) how the profitability index and the net present value are related.
Correct Answer
verified
Multiple Choice
A) -$5,474.76
B) -$1,011.40
C) -$935.56
D) $1,011.40
E) $5,474.76
Correct Answer
verified
Multiple Choice
A) -$2,021.28; reject
B) -$406.19; reject
C) $7,978.72; accept
D) $9,836.74; accept
E) $12,684.23; accept
Correct Answer
verified
Multiple Choice
A) greater than one.
B) greater than the cutoff point.
C) less than the cutoff point.
D) positive.
E) None of the above.
Correct Answer
verified
Multiple Choice
A) the initial cost of the project can be reduced.
B) the total amount of the cash inflows is reduced.
C) each cash inflow is moved such that it occurs one year later than originally projected.
D) the required rate of return is reduced.
E) the salvage value of the project is omitted from the analysis.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) initial cost increases.
B) required return for a project increases.
C) assigned discount rate decreases.
D) cash inflows are moved earlier in time.
E) duration of a project is lengthened.
Correct Answer
verified
Multiple Choice
A) I and II only
B) I and III only
C) II and III only
D) II and IV only
E) II, III, and IV only
Correct Answer
verified
Multiple Choice
A) the discount rate increases.
B) each cash inflow is delayed by one year.
C) the initial cost of a project increases.
D) the rate of return decreases.
E) all cash inflows occur during the last year of a project's life instead of periodically throughout the life of the project.
Correct Answer
verified
Multiple Choice
A) external rate of return.
B) internal rate of return.
C) average accounting return.
D) profitability index.
E) equalizer.
Correct Answer
verified
Essay
Correct Answer
verified
View Answer
Multiple Choice
A) accept the project because it returns almost $1.22 for every $1 invested.
B) accept the project because it has a positive PI.
C) accept the project because the NPV is $2,851.
D) reject the project because the PI is 1.05.
E) reject the project because the IRR exceeds 10%.
Correct Answer
verified
Multiple Choice
A) it considers the time value of money.
B) all relevant cash flows are included in the analysis.
C) it is easy and quick to calculate.
D) it is the most desirable of all the available analytical methods from a financial perspective.
E) it produces better decisions than those made using either NPV or IRR.
Correct Answer
verified
Multiple Choice
A) You should accept project B since it has the higher IRR and reject project A because you can not accept both projects.
B) You should accept project A because it has the lower NPV and reject project B.
C) You should accept project A because it has the higher NPV and you can not accept both projects.
D) You should accept project B because it has the higher IRR and reject project A.
E) You should accept both projects if the funds are available to do so since both NPV's are > 0.
Correct Answer
verified
Multiple Choice
A) there is only one sign change in the cash flows.
B) the first cash flow is always positive.
C) the cash flows decline over the life of the project.
D) there is more than one sign change in the cash flows.
E) None of the above.
Correct Answer
verified
Multiple Choice
A) easier for managers to comprehend than the net present value.
B) extremely accurate even when cash flow estimates are faulty.
C) ignored by most financial analysts.
D) used primarily to differentiate between mutually exclusive projects.
E) utilized in project analysis only when multiple net present values apply.
Correct Answer
verified
Multiple Choice
A) I and II only
B) II and III only
C) I and III only
D) I, II, and III
E) None of the above
Correct Answer
verified
Multiple Choice
A) discount rate applied to the project is increased.
B) initial cash outlay of the project is increased.
C) time period of the project is increased.
D) amount of each project cash inflow is increased.
E) costs of the fixed assets utilized in the project increase.
Correct Answer
verified
Showing 61 - 80 of 97
Related Exams