Filters
Question type

Study Flashcards

Make/buy/subcontract is typically considered at what time horizon when doing capacity planning?


A) Short-term
B) Medium-term
C) Long-term
D) It is not part of the capacity planning process.

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

Under Juran's Law, whenever a problem occurs, what percentage of the time is the problem the result of a system/process error?


A) 15 percent
B) 50 percent
C) 85 percent
D) 100 percent

E) B) and C)
F) A) and C)

Correct Answer

verifed

verified

Which of the following forms of capacity can only be determined AFTER the completion of activities?


A) Demonstrated capacity
B) Maximum capacity
C) Design capacity
D) Effective capacity

E) None of the above
F) B) and D)

Correct Answer

verifed

verified

The following sequence shows four operations for a computer chip assembly process and the effective capacity of each. Which step is the bottleneck? Step 1: 500 chips/hour Step 2: 250 chips/hour Step 3: 200 chips/hour Step 4: 550 chips/hour


A) Step 1
B) Step 2
C) Step 3
D) Step 4

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

C

You are given the following information. Which of these statements can you support with this information? You are given the following information. Which of these statements can you support with this information?   A) More capacity needs to be added in the short term to improve performance in the system. B) We have to look at the rate at which jobs are being input into the shop. C) Our workforce is not working hard enough. D) We need to further investigate whether the problem is in input or capacity.


A) More capacity needs to be added in the short term to improve performance in the system.
B) We have to look at the rate at which jobs are being input into the shop.
C) Our workforce is not working hard enough.
D) We need to further investigate whether the problem is in input or capacity.

E) B) and C)
F) C) and D)

Correct Answer

verifed

verified

Little's Law suggests that the key to increased throughput is:


A) Shorter flow times.
B) Fewer defects.
C) Eliminating waste.
D) Increased inspection.

E) A) and B)
F) All of the above

Correct Answer

verifed

verified

A bottleneck activity in a process is generally the activity with:


A) The smallest number of resources devoted to it.
B) The least capacity.
C) No delays in front of it.
D) The highest cost.

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

Which process activity is due to other factors (e.g., insufficient operating capacity, lack of material, equipment breakdowns) ?


A) Delay
B) Operation
C) Storage
D) Transportation
E) Inspection

F) A) and D)
G) C) and D)

Correct Answer

verifed

verified

A

Which of the following actions will NOT increase output?


A) Increasing capacity through physical additions.
B) Outsourcing.
C) Managing the flow of work into the system.
D) Changing the processes to eliminate unnecessary steps.

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

Which of the following statements about economies of scale is NOT true?


A) One reason economies of scale occur is because fixed costs can be spread over more units of production as output increases.
B) One reason economies of scale occur is because employees become more efficient as volume increases.
C) Economies of scale refers to the fact that as volume increases, total cost of production decreases.
D) Economies of scale may not exist at all levels of production.

E) None of the above
F) B) and C)

Correct Answer

verifed

verified

Adam Smith described his company's process as follows: "Under ideal conditions we can produce 10,000 units a day. However, our normal production is 6,000 units a day.Today, we actually produced 8,000 units." Which of the following is true?


A) Utilization is 60 percent of maximum capacity.
B) Yield is 133 percent of effective capacity.
C) Utilization was 133 percent of effective capacity.
D) All of these are true.

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

A manager is currently unhappy with the capabilities of a particular process and wants to improve its capabilities. To accomplish this, the manager needs to focus on the process:


A) Inputs, outputs, and flows.
B) Activities.
C) Management metrics.
D) Structure.

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

One implication of increased utilization in a process is that:


A) Process cost typically will go up.
B) Waiting time typically will go up.
C) Variance typically will be reduced.
D) All of these.

E) B) and D)
F) All of the above

Correct Answer

verifed

verified

B

A short-term, highly focused effort for improving a process is known as a:


A) Jidoka Event.
B) Kaizen Event.
C) Chaebol Event.
D) Poka-yoke Event.
E) Enchilada Event.

F) All of the above
G) A) and B)

Correct Answer

verifed

verified

Government regulations belong to which of the following elements of a process?


A) Activities
B) Inputs/outputs/feedback
C) Process structure
D) Management policies

E) C) and D)
F) None of the above

Correct Answer

verifed

verified

Process thinking causes managers to address critical process elements, including:


A) Activities.
B) Inputs and outputs.
C) Flows, structure, resources, and metrics.
D) All of these.

E) A) and B)
F) B) and D)

Correct Answer

verifed

verified

If a company can eliminate all sources of variance in a process:


A) It will be able to operate at maximum capacity at all times.
B) There will be no constraints in the process.
C) Continuous improvement will not be necessary.
D) None of these are true.

E) A) and C)
F) A) and B)

Correct Answer

verifed

verified

Most processes involve two basic types of flows:


A) Information flows and physical flows.
B) Product flows and decision flows.
C) Information flows and operator flows.
D) Physical flows and documentation flows.

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

An example of a short-term capacity decision is:


A) Adding specialized labor.
B) Installing new equipment.
C) Adding new facilities.
D) Adding low-skilled labor.

E) C) and D)
F) A) and B)

Correct Answer

verifed

verified

Kaizen Events are most appropriate for which type of operations problem?


A) Customer-based
B) Metrics-based
C) Process-based
D) Product-based

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

Showing 1 - 20 of 25

Related Exams

Show Answer