A) definitive
B) budgetary
C) final
D) ballpark
Correct Answer
verified
Multiple Choice
A) Determining the budget
B) Finalising the cost baseline
C) Controlling costs
D) Estimating costs
Correct Answer
verified
True/False
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
Multiple Choice
A) recurring
B) direct
C) sunk
D) intangible
Correct Answer
verified
Multiple Choice
A) directly related to performing the project.
B) those that cannot be allocated to projects.
C) those that can be easily controlled by managers.
D) not directly related to the products or services of a project.
Correct Answer
verified
Multiple Choice
A) Their main disadvantage is that they cost more than other techniques.
B) They are the only technique which do not require expert judgement.
C) They are most reliable when previous projects are similar in fact with current projects.
D) They use project characteristics in a mathematical model to estimate project costs.
Correct Answer
verified
Multiple Choice
A) budgetary
B) definitive
C) rough order of magnitude
D) final
Correct Answer
verified
True/False
Correct Answer
verified
Multiple Choice
A) Cost of machines to produce shoes
B) Salary paid to factory workers
C) Electricity used to run its factories
D) Cost of leather used to manufacture shoes
Correct Answer
verified
Multiple Choice
A) It can be used to estimate the projected time to complete the project.
B) It means that a project is behind schedule if an SPI is greater than one.
C) It means that a project is ahead of schedule if SPI is lesser than one or hundred percent.
D) It is the ratio of planned value to actual costs.
Correct Answer
verified
Multiple Choice
A) Cost forecasts
B) Work performance data
C) Change requests
D) Scope baseline
Correct Answer
verified
True/False
Correct Answer
verified
Short Answer
Correct Answer
verified
View Answer
True/False
Correct Answer
verified
Multiple Choice
A) It is used to allocate money into an organization's budget.
B) It provides an estimate of what a project will cost.
C) Its timeframe is always less than a year prior to project completion.
D) It is a type of estimate that is done in the final stages of a project.
Correct Answer
verified
Multiple Choice
A) cost controlling
B) cost estimating
C) cost budgeting
D) cost planning
Correct Answer
verified
Short Answer
Correct Answer
verified
True/False
Correct Answer
verified
Showing 21 - 40 of 100
Related Exams